Erection of 3700 M for 32” ~ 100” diameter under ground Reinforcement Concrete Pipe including 200,000 M3 of relevant earth work
225,000 inch-dia of Above Ground Piping Erection, 3,700 ton of Equipment Erection, 6,000 ton of Steel Structure, 230 km of Electrical Cable Works, Instrumentation, Insulation and Painting Works.
110,000 inch-dia of Steel Pipe Fabrication and Erection Works, 65,000 M of GRP Piping and 600,000 m3 of Earth Works |