Civil works:
SOUTH PARS PHASES 2&3 ONSHORE FACILITIES
FOUNDATION WORK (P/R, PIS, RECEPTION FACILITIES ,
PROCESSTRAINI)
LOCATION : Assaluyeh, Iran
OWNER : Total / Hyundai
TYPE OF CONTRACT : Sub-Contractor to HYUNDI
DESCRIPTION OF WORKS :

Construction of Pipe Racks, Pipe Sleepers, Tank Foundations, Reception Facilities, Process Trains, Flare Area, etc., involving 620,000 M3 of earthworks and 43,000 M3 of Concrete.