SOUTH PARS PHASES 2&3 ONSHORE FACILITIES
FOUNDATION WORK (P/R, PIS, RECEPTION FACILITIES ,
PROCESSTRAINI)
LOCATION :
Assaluyeh, Iran
OWNER :
Total / Hyundai
TYPE OF CONTRACT :
Sub-Contractor to HYUNDI
DESCRIPTION OF WORKS :
Construction of Pipe Racks, Pipe Sleepers, Tank Foundations, Reception Facilities, Process Trains, Flare Area, etc., involving 620,000 M3 of earthworks and 43,000 M3 of Concrete.